Blog

Why More Detail Doesn't Mean Better Planning

Jan 9, 20266 min read
Why More Detail Doesn't Mean Better Planning

There is a common belief in project planning that more detail equals better control. If the schedule has more activities, more logic links, more granularity — then surely it must be more accurate. More defensible. More useful.

In practice, the opposite is often true.

I have worked on programmes with thousands of activities where no one could explain the critical path. I have seen schedules so dense with logic that a single update triggered a cascade of unintended consequences. I have watched planning teams spend days maintaining detail that added nothing to decision-making.

More detail does not mean better planning. It often means worse planning — disguised as rigour.

The problem: false confidence

Over-detailed schedules create a specific kind of risk: false confidence.

When a programme has 5,000 activities, it looks thorough. It looks professional. It suggests that every aspect of the project has been thought through. Management sees the complexity and assumes the planning is solid.

But detail is not the same as understanding.

A pattern I see repeatedly

The detail captured tasks, not constraints. No one had identified the long-lead items, the outstanding approvals, or the interfaces that would actually drive the programme.

Here is a scenario I see repeatedly. A contractor builds an incredibly detailed schedule for a data center fit-out. Every cable tray, every containment run, every piece of equipment has its own activity. The logic is dense. The schedule runs to hundreds of pages when printed.

Six weeks into execution, the programme is useless.

Why? Because the detail captured tasks, not constraints. No one had identified that the main electrical switchgear had a 16-week lead time and was already late. No one had flagged that the raised floor installation depended on a design approval that was still outstanding. The schedule showed what would happen. It did not show what was stopping it from happening.

The detail created confidence. The confidence was misplaced.

The consequence: lost focus

When schedules become too detailed, planning teams lose focus on what actually matters.

Instead of asking "what are the key decisions we need to make this week?", they ask "how do we update these 200 activities?". Instead of identifying constraints and risks, they maintain logic links. Instead of influencing outcomes, they document history.

This is where most teams get stuck. The schedule becomes an administrative burden rather than a delivery tool. Planners spend their time on data entry. Project managers receive reports they cannot interpret. The critical path changes every week — not because the project has changed, but because the model is too sensitive.

I worked on a renewable energy project where the planning team maintained a schedule with over 8,000 activities. Every weekly update took two full days. By the time the report was issued, it was already out of date.

The level of detail was impressive. The level of control was poor. The team was so busy maintaining the schedule that they had no time to actually plan.

What actually matters: the right level of detail

The question is not "how much detail should a schedule have?" The question is "what level of detail supports the decisions we need to make?"

This varies by project stage and by audience.

During early planning, you need enough detail to understand the overall delivery strategy, identify major interfaces, and establish key milestones. You do not need every installation activity broken down to individual components.

During execution, you need enough detail to manage the current look-ahead period — typically 4 to 6 weeks. Beyond that window, excessive detail is speculation. It will change. Maintaining it wastes effort.

For different audiences, you need different views. A site supervisor needs a weekly task list. A project director needs milestone status and key risks. Giving both audiences the same 5,000-activity schedule serves neither.

The principle

Detail should enable decisions, not obscure them.

A better approach: simplify without losing credibility

Some planners resist simplification because they fear losing credibility. If the schedule looks simpler, will people think the planning is less thorough?

This is the wrong framing. Credibility comes from usefulness, not complexity.

A schedule that clearly shows the critical path, highlights constraints, and focuses attention on real risks is more credible than one that buries these things in thousands of activities no one reads.

Here is how to simplify without losing rigour:

Focus on logic, not just activities. A well-structured schedule with 500 activities and clear logic is more valuable than a poorly-structured schedule with 5,000 activities and broken links.

Separate planning levels. Use a summary-level programme for reporting and decision-making. Use detailed schedules at the work-front level for execution. Link them, but do not force one schedule to serve all purposes.

Capture constraints explicitly. Instead of hiding constraints inside logic, make them visible. What are the long-lead items? What are the key interfaces? What approvals are outstanding? These should be easy to find, not buried in a 200-page printout.

Review the critical path weekly — and explain it. If the critical path changes every update, either the project is genuinely volatile or the model is too sensitive. Understand which it is. A stable, explainable critical path is more valuable than a technically correct but constantly shifting one.

Ask: does this detail help us make a decision? If the answer is no, question whether you need it.

The trade-off

There is a trade-off, and it should be acknowledged honestly.

Less detail means less granularity in tracking. It means accepting that not every task will be individually scheduled. It means trusting execution teams to manage their own work within the framework the programme provides.

For some clients and contracts, this is difficult. There are environments where detailed schedules are contractually required, where earned value demands task-level tracking, where the culture expects complexity as a proxy for competence.

In these situations, you may need to maintain detail for compliance reasons. But even then, do not confuse the compliance schedule with the control schedule. Know which one you are using to actually manage the project.

Closing thought

Planning exists to support decisions, not to defend complexity.

A schedule is not a record of everything that could happen. It is a model of what needs to happen, in what sequence, with what dependencies and constraints. The purpose is clarity — not completeness.

If your programme has thousands of activities and you cannot explain the critical path in two minutes, the detail is not helping you. If your planning team spends more time updating the schedule than analysing it, the detail is not helping you. If your reports are so dense that no one reads them, the detail is not helping you.

Simplify. Focus. Make the schedule useful.

The best schedules are not the most detailed. They are the most useful. They show what matters, hide what does not, and give everyone involved a clear view of the path ahead.

About the author

Os Mohamed

Scheduling Manager at ACEN Australia and Founder of Nomad Strategic Project Services (Nomad SPS). I help teams deliver mission-critical projects with practical controls, strong scheduling systems, and modern tooling.

Continue

Related posts